Philippine National Oil Company

Browse over 46 requests from this government agency

Go Back
  • REQUEST SUBMITTED

    You have submitted an FOI request

    Date: 2019-05-26 14:02:48.577832

  • PROCESSING REQUEST

    Your request is already in review

    Date: 2019-05-27 07:26:40.896474

  • REQUEST DENIED

    Your request was denied

    Date: 2019-05-27 08:59:54.001452

  • 4

    RATE YOUR REQUEST

    How was your request?

Memorandum of Agreement between PNOC and NGCP on Mt Apo Geothermal Power Plant

Requested from PNOC by K. David at 02:02 PM on May 26, 2019.
Purpose: Research
Date of Coverage: 01/01/1994 - 12/31/1994
Tracking no: #PNOC-604571536180

David 02:02 PM, May 26, 2019

I would like to request for the copy of the Memorandum of Agreement signed by the PNOC, the National Grid Corporation of the Philippines, and the local governments of North Cotabato and Kidapawan City giving the province and the city direct lines from the Geothermal Powerplant 

The request is made in line with my research on Kidapawan history. 

Your swift response will be highly appreciated.

07:26 AM, May 27, 2019

May 27, 2019

Dear Karlo Antonio,

Thank you for your request dated May 26, 2019 under Executive Order No. 2 (s. 2016) on Freedom of Information in the Executive Branch, for Memorandum of Agreement between PNOC and NGCP on Mt Apo Geothermal Power Plant.

We received your request on May 26, 2019 and will respond on or before Jun 14, 2019 02:02:48 PM, in accordance with the Executive Order's implementing rules and regulations.

Should you have any questions regarding your request, kindly contact me using the reply function on the eFOI portal at https://www.foi.gov.ph/requests/aglzfmVmb2ktcGhyHgsSB0NvbnRlbnQiEVBOT0MtNjA0NTcxNTM2MTgwDA, for request with ticket number #PNOC-604571536180.

Thank you.

Respectfully,

Roberto Villa Jr.
FOI Officer

May 27, 2019

Dear Karlo Antonio David,

Greetings!

Thank you for your request dated May 26, 2019 02:02:48 PM under Executive Order No. 2 (s. 2016) on Freedom of Information in the Executive Branch.

Your request

You asked for Memorandum of Agreement between PNOC and NGCP on Mt Apo Geothermal Power Plant.

Response to your request

While our aim is to provide information whenever possible, in this instance this Office does not have  the information you have requested. However, you may wish to contact Energy Development Corporation  at www.energy.com.ph 

For further assistance you may review the FAQ section of the eFOI site: https://www.foi.gov.ph/help.

Your right to request a review

If you are unhappy with this response to your FOI request, you may ask us to carry out an internal review of the response by writing to Richard B. Tantoco, 38/F One Corporate Centre,Julia Vargas corner Meralco Avenue,Ortigas Center, Pasig City 1605 Philippines.  Your review request should explain why you are dissatisfied with this response, and should be made within 15 calendar days from the date when you received this letter. We will complete the review and tell you the result within 30 calendar days from the date when we receive your review request.

If you are not satisfied with the result of the review, you then have the right to appeal to the Office of the President under Administrative Order No. 22 (s. 2011).

Thank you.

Respectfully,
Manager Eleanor Rochelle Cruz
FOI Officer

Is this request offensive?

Requests for personal information and vexatious requests are not considered valid requests for Official Information.

If you believe this request is not suitable, you can report it for attention by the site administrators.